Project overview

Documented testing works on earthing systems associated with transformer plant, using clamp-type test instrumentation on earthing conductors and electrodes.

Works carried out

  • Inspection of earthing conductors and electrode connections
  • Earth resistance measurement with clamp-type instrumentation
Project documentation

Photographic record

Select a photograph to view it at full size.

Engineer using a clamp-type test instrument on an earthing conductor beside a power transformer bank
Earth resistance testing on transformer earthing conductors· Commissioning
Engineer beside a large distribution transformer with bushings, cable terminations and a steel tower structure behind
Utility power infrastructure — transformer and substation environment
Government & utility partnerships

Partnering for reliable power infrastructure

Pasajoegh welcomes collaboration with public institutions, utilities, developers and contractors delivering electricity infrastructure in Nigeria.

  • State Governments
  • State Ministries of Power
  • Electricity Distribution Companies
  • Federal Agencies
  • Renewable Energy Developers
  • EPC Contractors
  • Industrial Developers
  • Independent Power Producers
Discuss an infrastructure project